The GREEN LINE on 10th ave:
ONE GIANT SLASH THROUGH THE BELTLINE, GENERATIONS OF CONSEQUENCES

IMPERIAL STOUT.jpg

Billions of dollars. Permanent consequences.
Fundamental questions still unanswered.

Calgary's Green Line was supposed to transform transit in our city by connecting communities, improving mobility and supporting the city's growth for years to come. After more than a decade in planning, significant changes to the project and billions of dollars in public investment, we have to ask a fundamental question:

Are we still building the right project?

The current downtown and Beltline proposal raises major concerns about connectivity, capacity, safety, traffic, construction costs and the long-term viability of businesses along 10th Avenue.

It also leaves some very basic questions unanswered. How will the Green Line connect to the existing Red and Blue CTrain lines? How will it eventually extend into Calgary's north? How will trains operate through the downtown corridor without creating conflicts with vehicles, pedestrians and emergency services? And what happens to the businesses and communities that will live with the consequences of this infrastructure long after construction is finished?

We are not opposed to public transit. We believe Calgary needs a properly planned, integrated and reliable transit network.

But spending billions of dollars simply because a particular version of the project fits within the current funding envelope is not a substitute for good planning.Calgary deserves a transit system designed for the next 50 years, not a compromised solution that future taxpayers will have to fix.


We have raised these concerns directly with all levels of Government, including the Mayor, the Green Line team the majority of Councillors, the Premier, and the Transportion Minister. We still have many basic questions that do not have answers. These questions are practical, technical and fundamental, which are all deserving of answers. 
How can Calgary commit to permanent infrastructure before demonstrating how it will work as part of a complete transit system?

THE BIG QUESTIONS

60219.jpg
60264.jpg
60235.jpg
60229.jpg

Connectivity: where does the Green Line actually go?
A transit line is only as useful as the network it connects to. This version does not even come close to connecting to the Red and Blue C train lines.

Instead, passengers would need to make their way between stations, 2.5-3 blocks, including through the Plus 15 network. How is that considered proper integration of Calgary's existing transit network? City admin has stated that the Red and Blue lines are at capacity - so are they worried connecting the Green Line will overwhelm the current C-Train? If so, why are we not fixing that problem first? There is also no complete, publicly demonstrated plan showing how the Green Line will continue through downtown and connect to the future northern extension. We could/will spend billions building a line that operates as a disconnected segment for years, with future connections left to another phase, another budget and another Council. Where is the complete plan for connecting Calgary's transit network before we commit to building another disconnected piece of it?

Safety and traffic: what happens when rail and road compete for space?

The Green Line proposal introduces additional rail infrastructure and at-grade crossings into an already busy transportation network.The two proposed McLeod Trail crossings raise particular concerns about traffic congestion, signal interruptions, pedestrian safety and the movement of emergency vehicles. Especially during rush hour, and events at the new Event Centre, Casino, and BMO Centre. What happens during Stampede?

Calgary has already recognized the challenges associated with at-grade LRT crossings elsewhere in the city. Why are we not applying those lessons here?

How will the Green Line operate alongside vehicles, pedestrians, cyclists, businesses and emergency services without creating permanent conflicts?

10th Avenue: what happens to the businesses?
Not withstanding the fact that there are hundreds of reisidences along this corridor, this is also a functioning commercial street with businesses, employees, customers, deliveries, etc. The proposed alignment will change how these businesses operate permanently. Years of construction, changes to vehicle access, the loss or relocation of parking, utility work and the introduction of a new at-grade transit corridor will fundamentally change how this street work. The north side of 10th avenue has no alley access due to the CPKC rail tracks. Deliveries, waste collection, emergency access and everyday commercial operations cannot simply be moved somewhere else. What happens to the businesses that cannot operate during prolonged construction or once the permanent infrastructure is in place? These are not minor inconveniences. They are fundamental questions about the future of an established downtown business district. Why remove existing parking for a proposed public plaza in the parking lot at 2nd street? How will the City manage construction disruption and ensure the street remains viable? 

Cost and funding: is the cheapest option the right option? *(It isn't)
The argument that this is the most affordable option within the available funding does not establish that it is the best long-term investment.
We have raised concerns about early-stage cost estimates, provincial funding conditions and the decision not to pursue additional funding from the federal government for an underground alternative. What will this project ultimately cost, and what compromises are we making to build it? Calgary has already re-built the majority of its LRT stations numerous times, and with no plan for this train to go through the actual downtown, how much more money will it eventually cost future taxpayers? How long until citizens get fed up with the Mcleod trail at grade crossings and they have to pay to bury/cut&cover that portion of the train? The Green Line is only a 2 car LRT. How long until this train is at capacity like the current C-train?

THE TECHNICAL QUESTIONS THAT NEED ANSWERS

These are not hypothetical objections to transit. They are practical questions we have put to the Green Line team about how the proposed segment is supposed to function.The City has acknowledged that further design work is required. We understand that some details will evolve. But there is a difference between refining engineering details and committing to an alignment before the fundamental operational requirements are understood.
We initially asked this set of questions on Monday September 14th. To date we do not have any answers. See the full list below. 

GUIDEWAY AND TRAIN OPERATIONS

60253.jpg

The City's description of a guideway raises basic questions about how the system will operate within the available space.

  • Where exactly will trains turn around or switch back at the western end of the line?

  • Where will the switchback be located, and what will it physically look like?

  • How will trains reverse direction without significant delays or conflicts with other trains?

  • How many trains will be able to operate on the line at one time?

  • What service frequency will the design actually support?

  • When is the line expected to reach capacity, and what is the plan when it does?

  • What evidence demonstrates that the design will provide sufficient capacity for Calgary's future growth?

  • ​What happens when a train breaks down or there is an obstruction on the guideway?

60245.jpg

TRACK, OVERHEAD WIRES AND SUPPORTING INFRASTRUCTURE

The physical design will determine how much space the system occupies and how adjacent properties can function.

  • Will there be an inter-track barrier, such as a post-and-rail barrier? If so, where?

  • What will the overhead contact system look like?

  • Will poles and wires run throughout the downtown and Beltline segment?Will the system use SCAT-LP or SCAT, and can existing infrastructure be used?

  • Will the tracks be fully embedded in the roadway, or will any section between the Event Centre and Beltline use ballasted track?

  • If the tracks are not fully embedded, how will access to adjacent buildings be maintained?

  • Will systems buildings be required? If so, how many and where?

INTERSECTIONS, TRAFFIC AND SAFE CROSSINGS

60257.jpg

The Green Line will interact with some of Calgary's busiest transportation corridors. The City has already identified the challenges associated with at-grade LRT crossings elsewhere on the other lines so why would we introduce more of these conflicts into an already busy downtown transportation network without clearly demonstrating how they will be managed? The proposed crossings at McLeod Trail are particularly concerning.

  • How will trains move through the McLeod Trail intersections?

  • Will traffic signals be interrupted every time a train passes?

  • What impact will train movements have on vehicle queues and surrounding intersections?

  • How will pedestrians and cyclists safely cross the tracks?

  • Will vehicles be able to turn across the tracks?

  • What movements will be prohibited or restricted?

  • What happens when a train is delayed or stopped near an intersection?

  • Has the City modelled the cumulative impact of these interruptions on the surrounding road network?

  • How will the design accommodate increasing traffic volumes as Calgary continues to grow?

  • What will the at-grade crossings look like, particularly at both McLeod Trail crossings?

  • How will trains transition through intersections?

  • Can vehicles cross the tracks? If so, where and how?

  • Will vehicles need to travel onto tram-style rails through intersections, or will some movements no longer be possible?

  • How will pedestrians and cyclists safely cross the guideway?

  • What traffic modelling has been completed to assess signal delays, queues and congestion?

  • How will the design account for the traffic implications of Calgary's long-term growth?

  • Can these lighter trains be easily de-railed?

60255.jpg

GRADE SEPARATION: WHY ARE WE IGNORING OUR OWN LESSONS?

Reliable rapid transit requires infrastructure designed to move people safely, efficiently and consistently, without competing with vehicles, pedestrians and other road users for space. Grade-separated infrastructure, whether underground, elevated or within a dedicated corridor, eliminates many of the conflicts that can disrupt service and compromise safety. Calgary has already recognized the importance of this through its own planning studies. The City's 25 Avenue S.E. LRT Grade Separation Study specifically identifies how at-grade LRT crossings interrupt traffic signals and cause delays, and examines grade separation as a solution. The City supposedly understands the infrastructure challenges. Why aren't we applying those same lessons to the Green Line? If grade separation is ultimately recognized as necessary to eliminate conflicts elsewhere in Calgary, why are we designing another major transit corridor around at-grade crossings that could create similar problems?

60243.jpg

EMERGENCY ACCESS AND COMMERCIAL SERVICING

One of our biggest concerns is how the proposed infrastructure will affect access along 10th Avenue. Our building does not have an alleyway. We rely on street access for deliveries, waste collection, servicing and everyday business operations. The proposed arrangement will leave businesses sandwiched between the CPKC railway corridor and the Green Line.

  • How will police, fire and ambulance services access properties along 10th Avenue?

  • Will 10th Avenue remain a usable emergency access corridor?

  • What happens if a train breaks down or blocks access?

  • How will deliveries and commercial loading work?

  • Where will waste collection vehicles stop and operate?

  • How will businesses without access to turn into our loading zone receive supplies and service vehicles?

  • Will emergency vehicles be able to move through the corridor if a train is stopped?

  • What provisions have been made for businesses that need regular vehicle access to operate?

  • What permanent access restrictions will businesses face?

  • What arrangements will remain available during construction and service disruptions?

ENGINEERING MILESTONES AND COST ESTIMATES

The public should understand how developed the design is and how much confidence can be placed in the current cost estimate.

  • When does the City expect to reach Class 4, Class 3 and Class 2 estimates?What percentage of design completion does the current estimate actually represent?

  • What design milestones must be completed before a Class 2 estimate can be produced?

  • Will a Class 2 estimate be completed before the City commits to construction?

  • Will that estimate be publicly released?

  • What are the project timelines, and which major decisions remain outstanding?

SAFETY, TRAFFIC AND THE EXISTING TRANSIT NETWORK

60241.jpg

The Green Line should improve Calgary's transportation network. It should not introduce new problems while leaving existing ones unresolved.
WHY ARE WE REPEATING THE SAME TRANSIT SAFETY MISTAKES?
Calgary's public transit system has faced significant challenges with passenger confidence and safety, particularly since the pandemic. While ridership has been recovering, safety remains a major concern for many Calgarians . A May 2024 report by Global News, citing City of Calgary survey results, reported that 49% of Calgarians surveyed avoided taking the bus or CTrain because of safety concerns, up from 47% the previous year. The City also reported that respondents felt safer using buses than the CTrain.
Why, then, are we proposing another major piece of transit infrastructure without first addressing the safety and security concerns already affecting the existing system?
Calgary has also experienced challenges with transit station design, security and management. The history of the Chinook CTrain station, which was closed and subsequently reopened following significant changes, raises further questions about how the City intends to design, secure and maintain its transit facilities. The Green Line should be an opportunity to improve public transit in Calgary, not repeat problems that have already undermined public confidence. Passenger safety, security and the management of stations and surrounding public spaces need to be part of the design from the beginning, not treated as somebody else's responsibility after construction. WHY ARE GLOBAL BEST PRACTICES SUCH AS TURNSTILES AND BETTER FARE ENFORCEMENT OUTSIDE THE SCOPE?
When concerns about transit safety and security were raised with the Green Line team and the City, the response was that measures such as turnstiles and additional security were outside the scope of the project. How can something as fundamental as passenger safety be considered outside the scope of a major transit investment? International transit systems use a range of approaches to manage access, fares and security. Calgary should be examining those best practices rather than continually relying on additional enforcement after problems arise We believe the City and Province should seriously consider measures such as turnstiles as part of a broader transit safety and operating strategy. Without appropriate planning and management, communities and businesses along the line will face increased concerns about theft, robbery, fires, open drug use and nuisance activity. These outcomes are not inevitable, but they are risks that need to be considered and addressed before the system opens. Why are we waiting until problems develop instead of designing a safer and better-managed transit system from the beginning?

PLANNING AND FUNDING QUESTIONS

60247.jpg
60217.jpg

The engineering details matter, but they cannot be separated from the fundamental decisions about what Calgary is building, why this alignment was chosen and whether it represents the best use of public money.
ARE WE STILL BUILDING THE PROJECT CALGARY NEEDS/DESERVES?
After 11 years of planning, the project has obviously undergone significant changes. The current proposal is only shaped by the need to fit within existing funding rather than by a demonstration that it delivers the best overall transit solution. At what point do we stop defending the money already spent and ask whether the project being built today is worthy of the next 50 years of Calgary's growth?
WHY ISN'T THE CITY PURSUING AN UNDERGROUND OPTION WITH THE FEDERAL GOVERNMENT?
The Green Line FAQ states that the City is not currently seeking additional funding beyond the amounts already agreed to by the provincial and federal governments for Phase 1. We have pointed to support and reference letters from BILD, BOMA, NAIOP, the Calgary Downtown Association, the Victoria Park BIA and the Beltline Neighbourhoods Association, among others. If an underground route could better serve downtown while reducing impacts on businesses, why not present a business case and seek the additional funding required to evaluate it properly? 
WHAT ARE THE SPECIFIC CONDITIONS ATTACHED TO THE PROVINCIAL FUNDING?
We have asked whether changing the provincial baseline concept triggers another funding decision, and whether Calgary can retain the full $1.53 billion provincial commitment without further approval. We have also requested documentation confirming that all applicable conditions have been satisfied. These questions deserve clear answers because funding requirements can affect the options available to the City. For example, the Green Line was supposed to integrate into the downtown. This version does not do that, but is supposedly an accepted outcome by both the Federal and Provincial Governments. 
WHY COMMIT BEFORE THE WIDER RAIL NETWORK IS CLEAR?
The Passenger Rail Master Plan and the proposed passenger rail connection between Grand Central Station and Banff could have implications for downtown rail planning. We have asked how these plans will integrate with the Green Line and why the City should commit to a downtown alignment before the relevant connections and dependencies are sufficiently clear.
The City needs to show how today's design fits into tomorrow's network. If they are unable to do so, it exposes future taxpayers to massive risk and costs to fix a broken system.
ARE WE USING THE RIGHT EVIDENCE?
We raised concerns about City administration's reliance on a 2019 pedestrian heat map during the September 8 meeting. This heat map was from the plus 15 network and was used in part to determine the 7th ave and 2nd Street station. We question whether it adequately represents street-level pedestrian activity, particularly given its relationship to Plus 15 movement and the changes in downtown activity since COVID-19. We have asked for current mobility data, a clear explanation of the alternatives and evidence showing how the alignment will affect the surrounding transportation network.

WHO IS LOOKING OUT FOR CALGARY'S LONG-TERM INTERESTS?

60231.jpg

The Province is contributing significant funding to the Green Line, including a reported $1.53 billion commitment. That makes provincial oversight an important part of this conversation. The Province has previously intervened in the Green Line project when it determined that the proposed approach was not acceptable. Given the significant changes to the project since then, what role will the Province play in ensuring the current proposal is still a sound long-term investment? Will the Province independently examine the concerns being raised about connectivity, capacity, cost and the impact on downtown Calgary, or will it simply accept the City's decision to proceed? The Province has said it is committed to cost-effective transit investment that delivers long-term benefits. We agree with that objective. But what exactly are the long-term benefits of an alignment that does not provide a direct connection to the existing rail network and leaves the future northern extension unresolved? We are not questioning the value of a properly integrated LRT network. We are questioning whether this particular segment delivers that value. Does the GOA genuinely believe they are delivering great value for taxpayers? Do they recognize how the political priorities and decisions surrounding this project have shaped the outcome? And does City Council truly believe in what is being delivered? Are they content with the impact this alignment will have on the east end of the Beltline and parts of downtown, and the businesses and communities that call these areas home? Do those responsible for delivering the Green Line genuinely believe this is the best solution for Calgary, or has the desire to finally get something built taken priority over getting it right?

THERE IS AN ALTERNATIVE. WHY AREN'T WE CONSIDERING IT?

60223.jpg
60227.jpg

Rather than committing another $840 million to $1.6 billion to the current "downtown" and Beltline segment, the City should seriously consider ending the current construction at the Event Centre and redirecting those funds toward a better long-term solution. This would create an opportunity to properly plan the downtown and northern connection, resolve how the Green Line will integrate with the existing Red and Blue Lines, and potentially begin the northern extension sooner. It would also preserve the 10th Avenue business corridor, avoid years of disruptive construction, maintain important vehicle access into and out of downtown, and allow the City to properly address the significant traffic and safety concerns surrounding the McLeod Trail crossings. The City could divert that money to starting the Northern segment as a BRT with the groundwork laid for the Green Line LRT. We are not about abandoning the Green Line. We are about reconsidering a segment that has many issues around connectivity, capacity, cost and long-term negative impacts on downtown Calgary. The money potentially saved or redirected could instead support the transit infrastructure Calgary actually needs, while also freeing up taxpayer dollars for other priorities such as policing, public safety and essential City services. I have raised this alternative with members of Council and the Province. Unfortunately, there does not appear to be much appetite to reconsider the current approach unless additional provincial funding becomes available. I believe that is the wrong way to look at it. The question shouldn't simply be to blame the province. It should be whether this is the right plan to spend that money on in the first place. There is still an opportunity to change direction before we commit billions more to infrastructure that may create problems for decades. We can protect downtown, deliver meaningful transit investment to northern communities and build a system that connects Calgary properly. We don't have to abandon the vision of the Green Line. We need to stop treating this particular alignment as the only way to achieve it.

WHAT WE WANT TO SEE BEFORE THIS PROJECT MOVES FORWARD

Calgarians deserve answers before more irreversible decisions are made.We believe the City, Province and GreenLine team should:

  • Publish a complete connectivity plan showing how the Green Line will connect to the Red and Blue Lines, continue through downtown and eventually extend north.

  • Provide clear engineering and operating details explaining how the tracks, trains, intersections, crossings and emergency access will function.

  • Demonstrate the real costs of the current proposal, including the future connections and infrastructure required to deliver a complete transit system.

  • Seriously compare alternatives, including going back underground, based on long-term value rather than simply the ability to fit within current funding.

  • Address transit safety and security as part of the planning and design, not as an issue to be dealt with after the system opens.

  • Provide a meaningful plan for affected businesses and residents, including access, deliveries, construction staging, public-space management and long-term operations.

  • Reconsider whether the current downtown segment is the best use of public money, particularly when those funds could potentially be redirected toward the northern extension and a better-connected transit network.

CALGARY DESERVES BETTER

We are not opposed to transit. We are opposed to spending billions of dollars on infrastructure that has not been demonstrated to be the right solution. Around the world, modern rapid transit systems are designed to keep trains physically separated from vehicle and pedestrian traffic. Cities have long recognized that reliable rapid transit requires infrastructure should move people safely and efficiently without competing with road traffic. Calgary should be no different. Running the Green Line at street level through busy urban corridors creates conflicts with vehicles, pedestrians, cyclists and emergency responders. These are not minor design inconveniences. They are fundamental infrastructure and operational challenges that will affect how the system functions forever. The Green Line is an opportunity to build something that will serve Calgary for all time. That opportunity should not be wasted by rushing forward with an alignment that raises so many unanswered questions. The cost of getting this wrong will not just show up on a project budget, it will be measured in lost businesses, diminished downtown access, compromised connectivity and decades of missed opportunity. We have already invested years and significant public money into this project. That investment should not become a reason to ignore problems with the current plan. There is still time for our City Council and the Province to reconsider the approach, protect downtown Calgary and deliver meaningful transit investment to communities that have been waiting for it. Build the right project. Not simply the cheapest one. Calgary deserves a transit legacy, not an expensive problem for future generations to fix.